Two-Year Effort to Widen Route 29 Begins Tuesday

The work will cause intermittent lane closures and slowdowns, according to PennDOT.

On Tuesday, July 31, PennDOT will begin a construction project to improve and add lanes to Morehall Road (Route 29) near the turnpike in East Whiteland and Charlestown townships. The projected completion date for the project is June 2014. 

What does the work mean for traffic? According to the PennDOT press release: "Motorists traveling through the Route 29 (Morehall Road) construction area will face intermittent lane closures and possible slowdowns weekdays from 9 a.m. to 3 p.m."

The work will begin with crews clearing brush and vegetation from the side of the road and installing drainage inlets.

Find out what's happening in West Chesterwith free, real-time updates from Patch.

Here's the full release from PennDOT:

PennDOT to Start $4.2 Million Project to Improve Travel on Route 29 in Chester County 

Find out what's happening in West Chesterwith free, real-time updates from Patch.

King of Prussia – The Pennsylvania Department of Transportation today announced that preliminary work will start Tuesday (July 31) on the $4.2 million project to improve travel on Route 29 (Morehall Road) in Charlestown and East Whiteland townships, Chester County. 

PennDOT will widen Route 29 (Morehall Road) to provide an additional northbound and southbound through lane between Yellow Springs Road and Phoenixville Pike/Charlestown Road to enhance traffic flow and reduce congestion. This part of Route 29 carries 15,000 vehicles day.

The improvements on Route 29 (Morehall Road) also will include five-foot wide shoulders; intersection upgrades and new signals at Yellow Springs Road/Warner Lane, Whitehorse Road and Charlestown Road/Phoenixville Pike; and storm water management facilities. 

PennDOT’s contractor also will widen Charlestown Road from Phoenixville Pike to just south of the Charlestown Elementary School to provide an additional through lane in each direction and shoulders; widen Phoenixville Pike east of Charlestown Road to provide an additional westbound left turn lane; widen Phoenixville Pike west of Charlestown Road to provide a gore area opposite the dual left turn lanes; and widen Yellow Springs Road to add an exclusive right turn lane.

Construction is scheduled to finish by June 2014.

Initially, crews will clear brush and vegetation from alongside Route 29 (Morehall Road) and install filter bags inside drainage inlets.

Motorists traveling through the Route 29 (Morehall Road) construction area will face intermittent lane closures and possible slowdowns weekdays from 9 a.m. to 3 p.m.

Allan A. Myers, LP of Worcester, Montgomery County is the general contractor on the $4,237,948 contract. Construction is financed with state funds plus monies provided by the Pennsylvania Turnpike Commission and LV Associates. The Trammell Crow Company funded the project’s engineering design phase.

PennDOT reminds motorists they can log on to www.511pa.com or call 511 from any phone to check traffic conditions on major highways before heading out.

For more information, visit www.dot.state.pa.us. Follow local PennDOT information on Twitter atwww.twitter.com/511PAPhilly.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here